Day 27 – Pool Construction – Drains

For the first time in almost a month, some work was done on our pool. They started installing the drains for the deck.



Day 26 – Pool Construction – Ledgestone Work

Work continued on the ledgestone today with everything but around the spill from the spa being finished. We are very happy with the way it looks. It goes with the slide structure perfectly!



Day 25 – Pool Construction – Ledgestone Started

They started putting on the ledgestone today. It looks absolutely gorgeous! There is definitely an art to putting on the ledgestone. There are a bunch of pieces and they have to be arranged just so, to get a balanced look. The guy doing our ledgestone puts a lot of effort into making it look just right. He does an awesome job.




Day 24 – Pool Construction – Tile Work

They started putting on the tile today. They got most of it done, except around the skimmer and the spill from the spa.




Day 23 – Prep For Tile – Pool Construction

Today the workers create a band with mortar where the tile will go. The tile will be at the waterline all around the pool, except for where the slide structure is located. Above the waterline on the spa and back part of the pool will be ledgestone.



Day 22 – Pool Construction – Coping Finished, Rest of Gunite Removed

The workers poured the rest of the coping today and removed the remaining gunite from the backyard. As the pool gets closer and closer to be finished, the kids get more and more excited. We all can’t wait till we can dive in!




Day 21 – Pool Construction – Coping Poured, Coping Forms Put on Spa, Removal of Gunite from Backyard

They poured the concrete for part of the coping for the pool today. We went with a colored concrete and I really like how it turned out. They also got the forms on the spa and started removing the gunite that was in the backyard.




Day 20 – Pool Construction – Continued Work On The Forms

Work continued on the forms for the coping today, adding the foam forms to one side of the pool.



Day 19 – Pool Construction – More Work On The Forms

Work continued on the forms for the coping today.



Day 18 – Pool Construction – More Forms and Color On Slide

Work continued on the forms for the coping today. In addition, the workers added color to the slide.



Over the weekend, Dan finished raising the height of the wall. He took off the top row, then added three new rows.





