Work continued on the pavers today. We really love how they look and are so glad we went with the pavers over the concrete.
My chaotic life raising six kids
Work continued on the pavers today. We really love how they look and are so glad we went with the pavers over the concrete.
They finished putting down the sand and started placing the pavers today.
They installed the copper mess around the pool today. This is a new requirement by the city and supposedly it is to prevent electrocution of people standing on the pavers if the pool gets hit by lightening. The also started putting down the sand that the pavers will sit on.
The new gas meter was installed today. An upgraded meter was needed to handle the additional capacity required for the pool heater.
Today they started putting ledgestone on the planters.
Today they started construction on the planter next to the slide.
The pipes for the pool equipment were painted to match the rest of the equipment today.
The electrical connections for the pool equipment were done today. This included hooking up the lights for the pool.
Paver prep work continued today. They also started installing the pool equipment.
Today they started getting the ground ready for the pavers that will go around the pool.